Offshore Project Progress – 7 August

0

Block Island

Barge incident: One of the legs of the first of Block Island’s five jacket foundations has been slightly damaged after a barge hit it.

The barge was being used during the 30MW project’s construction, but no impact on the construction timetable is expected.

Set to become the USA’s first offshore wind farm, Block Island is begin developed by Deepwater Wind in Rhode Island Sound.

Construction at the site started on 27 July. It is due for completion in 2016. 3-Aug-15

 

Horns Rev 3

Surveys begin: Seabed surveys and data gathering are under way, at the site of the planned Horns Rev 3 project.

The 400MW wind farm is being developed by Vattenfall, in the North Sea off Esbjerg.

MHI-Vestas was named as the preferred turbine supplier for the project in June.

In February, Vattenfall was awarded the licence to develop the Horns Rev 3 project. Vattenfall placed a winning bid of €103.1/MWh to secure the contract from the government. 4-Aug-15

 

Nobelwind

Cabling contract: Prysmian will supply the inter-array cables to the 165MW Nobelwind (Bligh Bank Phase II) project off Zeebrugge, Belgium.

It will design, manufacture and supply the 33kV cables and provide termination and testing services.

The cables will be manufactured in Drammen, Norway, and installed at the North Sea project site by the first half of 2017.

Bladt Industries and Semco Maritime were contracted by developing consortium Nobelwind NV to supply the offshore substation to the project in June. 5-Aug-15

 

Westermeerwind

Vessel charter: MPI Workboats has secured a 15-year charter for the MPI Dorothea vessel at Westermeerwind.

The vessel will work for Siemens, out of Lemmer, Friesland, northern Netherlands.

The 144MW wind farm — the near shore part of the Noordoostpolder project — is under construction in the Ijsselmeer and due for completion in 2016.

It will comprise 48 Siemens SWT-3.0-108 turbines. Cable installation was completed in July. 5-Aug-15

 

Humber Gateway

Project online: E.on’s Humber Gateway is now fully operational and only minor works remain ongoing, the developer has confirmed.

The 219MW wind farm comprises 73 Vestas V112-3.0 MW turbines and lies in the North Sea, off Holderness, Yorkshire.

First power was produced from the project in February. 5-Aug-15